This project consists of operational improvements Guadalupe River to FM 306 and 1/3 miles south of FM 306 to FM 306 in New Braunfels.

Need & Purpose

  • Improve safety and mobility

Project Description

  • Operational improvement including the widening of the frontage roads in the areas where new entrance and exit ramps are constructed from 1.3 miles south of FM 306 to FM 306. The following new ramps will be constructed under this contract.
    • I-35 NB Exit Ramp to FM 306
    • I-35 NB Entrance Ramp from Business 35
    • I-35 SB Exit Ramp (south of FM 306) to Business 35
    • I-35 SB Entrance Ramp (south of FM 306) near N. Kowald Ln.
  • Operational improvements at I-35 and FM 306 intersection including the construction of concrete pavement and construction of a Partial Displaced Left Turn at the south of end of the I-35 bridge.
  • Work will also include signal upgrades at I-35 and FM 306 and the construction of sidewalks and curb ramps at the intersection along the project limits.

Funding

  • Construction cost: $18.4 million

Schedule

  • Construction began in September 2019 and is expected to be completed in 2022.
  • Currently 93% completed

Downloads

CONTACT

Public Information Officer
(210) 615-5839
Email

TxDOT San Antonio District
4615 NW Loop 410
San Antonio, TX 78229-0929

©2022 Texas Department of Transportation • All Rights Reserved