I-35 from FM 2001 to FM 150

Overview:

This project consists of ramp reversals, intersection improvements and new U-turn bridges between FM 2001 in Buda and FM 150 in Kyle.

Need & Purpose
  • Need for improved traffic flow
  • Congestion reduction
  • Alleviate bottlenecks
Project Description
  • Construct and reconfigure eight entrance and exit ramps
  • Widen the Robert S. Light bridge
  • Construct seven U-turn bridges at Kyle Crossing, FM 1626, Robert S. Light and FM 2001
Funding
  • Construction funded by Hays County Road Bond Pass-Through Financing Agreement with TxDOT
  • Construction cost: $11.6 million
Schedule
  • Finalized schematic and environmental documentation: April 2013
  • Plans Specifications and Estimates: June 2012 – May 2013
  • Construction letting: August 2013
  • Construction start: January 2014
  • Construction completion: January 2016