I-35 from Kyle Crossing to RM 150

Overview:

This project consists of ramp reversals for four northbound I-35 ramps between Kyle Crossing and RM 150.

Need & Purpose
  • Improve safety and mobility
Project Description
  • Reverse northbound ramp configurations between Kyle Crossing and RM 150
  • Construct an auxiliary lane, or extended entrance/exit lane, along the northbound frontage road between Kyle Crossing and FM 1626
  • Reconstruct the existing northbound frontage road between FM 1626 and RM 150, including the addition of an extended entrance/exit lane and a new bridge over Plum Creek between the two reversed ramps
Funding
  • Project development funded by TxDOT
  • Construction not funded
  • Construction cost estimate: $22.8 million
Schedule
  • Finalized schematic and environmental documentation: anticipated winter 2016/2017
  • Begin Plans Specifications and Estimates (PS&E) documentation: April 2016
  • Complete PS&E: anticipated spring 2018
  • Construction letting: anticipated spring 2018*
  • Construction start: anticipated summer 2018*
  • Construction completion: anticipated summer 2019*

*Dates are contingent on funding.