I-35 from north of River Ridge Parkway
to south of Loop 82

Overview:

This project consists of new northbound I-35 ramps between River Ridge Parkway and Loop 82 (Aquarena Springs Drive). A northbound exit ramp to River Ridge Parkway would be constructed and an existing northbound entrance ramp south of River Ridge Parkway would be relocated to provide adequate weaving distance.

Need & Purpose
  • Improve safety and mobility
Project Description
  • Construct northbound exit ramp to River Ridge Parkway
  • Relocate existing northbound entrance ramp south of River Ridge Parkway to provide adequate weaving distance
  • Reconstruct the northbound frontage road between River Ridge Parkway and Loop 82
Funding
  • Project development funded by TxDOT
  • Construction not funded
  • Construction cost estimate: $11.9 million
Schedule
  • Finalize schematic and environmental documentation: anticipated winter 2016/2017
  • Begin Plans, Specifications and Estimates (PS&E): anticipated summer 2016
  • Complete PS&E: anticipated spring 2018
  • Construction letting: anticipated spring 2018*
  • Construction start: anticipated summer 2018*
  • Construction completion: anticipated summer 2019*

*Dates are contingent on funding.

Get Involved
Downloads

Project Vicinity Map

I-35 from River Ridge Parkway to Loop 82

Contact

Public Information Officer

TxDOT Austin District
P.O. Box 15426
Austin, TX 78761-5426

(512) 832-7000

Email