Overview:

The project includes the construction of a diverging diamond intersection, which is an innovative intersection to alleviate an existing bottleneck at the intersection of FM 734 (Parmer Lane) and I-35. The project also includes operational improvements at the Lamar Boulevard and Parmer Lane intersection.

Need & Purpose
  • Improve safety and mobility, including:
    • Improve traffic flow due to a high volume of left-turn traffic
    • Accommodate turning movements onto and from Parmer Lane
    • Eliminate the need for left-turn bays and left-turn signal phases
    • Minimize the number of potential conflicts between through traffic and left-turn traffic
Project Description
  • Replace the traditional intersection with a diverging diamond intersection
  • Add a southbound collector-distributor road, or intersection bypass lane
  • Reconstruct two entrance and exit ramps south of Parmer Lane
  • Construct right-turn lanes at the intersection of Lamar Boulevard and Parmer Lane
  • Construct dual left-turn lanes from Parmer Lane to Lamar Boulevard
  • Improve bicycle and pedestrian accommodations
Funding
  • Project development funded by TxDOT
  • Construction cost estimate: $25 million
Schedule
  • Finalize schematic and environmental documentation: anticipated spring 2017
  • Begin Plans, Specifications and Estimates (PS&E): anticipated summer 2017
  • Complete PS&E: anticipated summer 2018
  • Construction letting: anticipated fall 2018*
  • Construction start: anticipated winter 2018/2019*
  • Construction completion: anticipated summer 2020*

*Dates are contingent on funding.