I-35 at RM 1431

Overview:

The project includes the construction of a Diverging Diamond Intersection, which is an innovative intersection to alleviate an existing bottleneck at the intersection of RM 1431 and I-35. The project also includes construction of a southbound collector-distributor road, or intersection bypass lane, and ramp improvements.

Need & Purpose
  • Improve mobility and safety to:
    • Improve traffic flow due to a high volume of left-turn traffic
    • Accommodate turning movements onto and from University Drive
    • Eliminate the need for left-turn bays and left-turn signal phases
    • Minimize the number of potential conflicts between through traffic and left-turn traffic
Project Description
  • Replace traditional intersection with a Diverging Diamond Intersection
  • Add southbound intersection bypass lane
Funding
  • Traditional development by TxDOT
  • Construction cost estimate: $6.6 million
Schedule
  • Finalized schematic and environmental documentation: April 2014
  • Plans, Specifications and Estimates: February 2013 – April 2014
  • Construction letting: June 2014
  • Construction start: October 2014
  • Construction completion: May 2016