TXDOT HEAVY EQUIPMENT OPERATORS: IS THIS JOB RIGHT FOR YOU?

It may be a cliché, but it's still true that big trucks fascinate many people. Social media often features photos of small boys enthralled by big trucks working nearby. And there's even a heavy equipment playground for grownups called "Dig This" in Las Vegas, Nevada, that (for a fee) lets grown-ups operate bulldozers, loaders and excavators for fun. | Read More

CONSTRUCTION UPDATES

SECTION 2B: TEMPLE (S. LOOP 363 TO N. LOOP 363)

Access this section's project map (schematic).

DOWN THE ROAD

  • Continue constructing the northbound mainlanes and northbound frontage road overpasses at the BNSF Belco Yard railroad.
  • Continue constructing northbound mainlane pavement from Adams and Central Ave. Interchange north to the BNSF Belco Yard overpasses.
  • Continue constructing northbound mainlane pavement from BNSF Belco overpass north through the remainder of the project.
  • Continue installation of retaining wall No. 1.
  • Continue construction of the BNSF underpass.
  • Continue construction of the BNSF Lampasas Sub northbound mainlane overpass.
  • Continue construction of Retaining Wall 52 north of Nugent Ave.
  • Continue construction of the west side of the Adams/Central Ave. Interchange.

SECTION 3A-1: TEMPLE TO TROY (N. LOOP 363 TO N. TROY CITY LIMIT)

Access this section's project map (schematic).

MILESTONES

  • Completed paving the south-to-north turnaround at the North Troy intersection.
  • Completed paving the north-to-south turnaround at the Berger/Hart Rd. intersection.
  • Completed paving the north-to-south turnaround at North Troy intersection.
  • Completed pouring the asphalt for the northbound frontage road north and south of the FM 1237 intersection.
  • Opened crossing at FM 1237/Pendleton Rd. to one lane in each direction.

DOWN THE ROAD

  • Complete installing signs for the new southbound mainlanes.
  • Continue working on the east half of the northbound frontage road from FM 935 to North Troy.
  • Continue working on the northbound frontage road between Berger/Hart Rd. and FM 1237.
  • Continue working on the North Troy intersection, Berger/Hart Rd. intersection, FM 1237 intersection and West Main Street/FM 935.
  • Switch traffic at northbound mainlanes and mainlanes north of Berger/Hart Rd. to the outside and middle lanes.
  • Begin pouring the permanent central barrier wall at the mainlanes north of Berger/Hart Rd.

SECTION 3A-2: TROY TO BRUCEVILLE-EDDY (N. TROY CITY LIMIT TO WOODLAWN RD.)

Access this section's project map (schematic).

MILESTONES

  • Opened the new Big Elm Rd. intersection with one lane open in each direction.
  • Switched traffic onto new concrete paving on southbound mainlane pavement between Big Elm Rd. and Big Elm Creek.
  • Poured the deck for the new southbound mainlane bridge over Big Elm Creek.
  • Set beams and poured the bridge deck for the new southbound mainlane bridge over Big Elm Creek.
  • Began constructing new drainage structures along the northbound frontage road between Old Blevins Rd. and FM 107.
  • Began work on the new northbound mainlane pavement between North Eddy and Old Blevins Rd.

DOWN THE ROAD

  • Continue construction on the new southbound frontage road at FM 107.
  • Continue paving the northbound frontage road between Old Blevins Rd. and FM 107.
  • Continue constructing new drainage structures along the northbound frontage road between Old Blevins Rd. and FM 107.
  • Continue working on the east retaining wall at the new FM 107 underpass.
  • Continuing working on the west retaining wall rail and riprap placement.
  • Continue paving the southbound mainlanes between North Eddy and Old Blevins Rd.
  • Continue constructing new drainage structures along the northbound frontage road between Old Blevins Rd. and FM 107.
  • Continue placing concrete paving on southbound mainlane pavement between Big Elm Rd. and Big Elm Creek.
  • Begin working on remainder of southbound pavement.
  • Continue working on rail for the new southbound mainlane bridge over Big Elm Creek.
  • Continue building additional lanes and turnarounds at Big Elm Rd.
  • Continue working on the new intersection of the northbound frontage road and FM 107.
  • Complete new northbound pavement from the railroad to the north end of project.

SECTION 4A: WACO ACCESS ROADS (MLK TO TAYLOR)

Access this section's project map (schematic).

LANE CLOSURES

  • North-to-south access roads and the turnaround from MLK Blvd. under I-35 at the UPRR crossing have been permanently closed. New access roads and railroad crossing bridges will be constructed to replace them.
  • The southbound frontage road turnaround between Forrest St. and UPRR has been closed permanently at Cherry St.
  • Forrest St. Bridge is closed.

MILESTONES

  • Completed construction of new Forrest St. bridge drill shafts.

DOWN THE ROAD

  • Continue construction of the northbound and southbound frontage-road bridge rails.
  • Continue to work on opening the new frontage roads.
  • Continue construction of new Forrest St. bridge (currently working on drilled shafts).
  • Continue to work on tie-in point for the new southbound frontage road to the existing frontage road.
  • Construct the new northbound on-ramp from MLK Blvd.
  • Complete northbound and southbound bridge retaining walls at Forrest Ave. bridge.
  • Complete construction of columns in the center median for the Forrest Ave. bridge.
  • Complete building of abutments for the Forrest Ave. bridge.
  • Hang beams for the Forrest Ave. bridge.
Top
My35 logo

Central Texas News

Contact

Jake Smith
I-35 Public Information Officer
254-867-2705
Contact My35

TxDOT Waco District
100 S. Loop Drive
Waco, TX 76704
CALENDAR

Future Events Being Planned

We're now scheduling evening project-update meetings for the communities along I-35. If you'd like to have one in your area, call us and we'd be glad to get it set up for you.