Skip to main content

My35 Central Texas Newsletter: September 2022

Volume 12, Number3


New and Improved

The completion of the I-35 Waco Project is right around the corner. TxDOT expects to finish the section in November 2022, offering I-35 travelers one more reason to celebrate this holiday season, says Texas A&M Transportation Institute (TTI) Research Engineer John Habermann. Habermann is the mobility coordinator who liaisons between TxDOT and the local community to lessen the impact of construction. "From a shift in how folks choose to travel to a worldwide pandemic, there was ample opportunity for something to go wrong on this project," he says. "But almost everything went better than we could have hoped." | Read More

Construction Updates

Section 4B: Waco (12th Street to North Loop 340)

Access this section's project map (schematic).

Milestones

  • Switched all northbound mainlane traffic onto new pavement through the whole project.
  • Opened all entrance and exit ramps.
  • Switched westbound US 84 / Waco Drive to new pavement.
  • Paved and opened 2nd Street off the southbound frontage road.
  • Switched traffic to new pavement on Business 77.

Down the Road

  • Continue to open the following sections of the northbound frontage road:
    • 11th/12th Street area.
    • North of University Parks Drive.
    • North of US 84.
  • Continue sidewalk and driveway construction for the northbound and southbound frontage roads from Behrens Circle to 12th Street.
  • Finish paving Hogan Lane east of the northbound frontage road.
  • Continue setting the northbound and southbound retaining wall between US 84 and Behrens Circle.
  • Continue the east-end headwall and riprap construction of Culvert 5 (Waco Creek).
  • Continue paving intersections at 4th/5th Streets and 11th/12th Streets.
  • Continue cross-street paving of the westside of University Parks Drive.
  • Continue drilled shaft installation for new traffic signals.
  • Continue installation of new signal hardware including pedestrian crossing signals.
  • Continue landscaping/flat work at multiple interchanges.
  • Install pedestrian barrier between Behrens Circle and Loop 340.
  • Complete retaining walls at the Brazos River.
  • Complete side streets/driveways at:
    • The northbound frontage road/east side.
    • Two driveways for the Exxon station along 5th Street.
    • The driveway for the Baylor welcome center.
    • Price Street.
    • Oak Street at Forrest Street.
    • Taylor Street along BUS 77.
    • Driveway adjacent to Taylor Street and BUS 77.
    • TxDOT driveway BUS 77.
    • Boston and Brame.
    • Parrish Street tie-in.
    • Hogan Lane.

I-35E Expansion (I-35 East/West split to Ellis County line)

Milestones

  • Switched northbound I-35E traffic onto the new concrete pavement for Phase 4.
  • Completed the I-35E southbound exit to US 77.
  • Temporarily closed the northbound exit and entrance ramps at FM 934.
  • Established permanent vegetation and soil stabilization.

Down the Road

  • Ongoing construction of the northbound mainlanes, including earthwork, culverts, retaining walls, paving, and bridge construction at White Rock Creek.
  • Complete concrete paving on FM 2959 and FM 934.
  • Complete the construction of the northbound exit and entrance ramps at FM 934 and reopen to traffic.

Top

My35 logo

Central Texas News

Contact

Jake Smith
I-35 Public Information Officer
254-867-2705
Contact My35

TxDOT Waco District
100 S. Loop Drive
Waco, TX 76704
Calendar

Future Events Being Planned

We're now scheduling evening project-update meetings for the communities along I-35. If you'd like to have one in your area, call us and we'd be glad to get it set up for you.

My35 logo

Sign up!

for My35 Main Street Texas News

©2022 Texas Department of Transportation • All Rights Reserved